LIST OF TURNKEY PROJECTS EXECUTED - OFFSHORE
Client | Name of Project | Engineering / Pro-curement/ Fabrication /Installation/ Platform Modifications/ Revamp/Hook-up/ Testing / Pre-commissioning / Start-up/ Commissioning | Contract Award Date |
Completion Dates | ||
ONGC | Balance Topside Modification Work Pipeline Replacement Project VI | The scope involves work related to balance topside modification on Panna along with Pre-construction survey, design, engineer, procurement, fabrication, load out, transport all items required (viz. pipes, fittings, specialty items, cables, tubing, cable trays, instruments & pipe supports, structural steel, clamps, Installation of 3 numbers MOL pump, 3 Nos Booster Pumps, HT Container & Battery Container, modifications on existing facilities, Hook-up, Testing, Pre- commissioning and commissioning (as applicable) of entire facilities for topside modification and make system ready for commissioning and commissioning assistance | 27.01.2023 | 07.05.2023 FOR HVAC- 31.08.2023 |
||
ONGC / Main Contractor - L&T | Pipeline Replacement Project VII RTR (PRP- VII RTR) | As a Subcontractor for Execution of Offshore Hook-up, Modification and Commissioning under PRP VII project | 21.11.2022 | Season I - 15.05.2023 Season II - 15.05.2024 |
||
ONGC | Platforms Makeover Project Tender 1 (PMPT1) | The revamp work mainly consists of replacement of grating, handrails, chequered plates and repair/ replacement of supporting structural steel. New painting of replaced/ repaired items are included in scope of work. These repair/ replacement works shall be carried out on 41 platforms of MH Asset and N&H Asset. The contractor shall be required to carry out Survey including pre-engineering, pre-construction and post-construction, Design Enginering, Procurement, Fabrication, Transportation, Installation pertaining to repair and replacement works on above platforms. | 28.10.2022 | 31.03.2025 | ||
ONGC | Cyclone Tauktae Rehabilitation Project of B&S Asset on LSTK basis | The scope of works covers revamping by replacement of damaged materials like gratings, chequered plates, hand railing and other miscellaneous structural materials, Mechanical equipements, piping, cable, cable trays, support materials and other miscellaneous items at platforms B&S assets | 20.06.2022 | 04.09.2023 | ||
ONGC | Hiring of Services fro Hook-up, Testing & Commissioning (HUTC) for Sagar Samrat MOPU | Provision of manpower (60 persons) for hook-up, testing, pre-commissioning and commissioning of MOPU Sagar Smrat Jacked up at WO-16 location and bridge connected with WO-16 Well Platforms with required tools and tackles, consumables, scaffolding materisl etc. | 21.05.2022 | 6 Months Extended till 31.01.2024 | ||
ONGC | Replacement of Hot Oil Expansion Tank of MH Asset Platforms on LSTK Basis | The scope of work covers existing Hot Oil Vessel are corroded and need replacement due to deteriorating condition & aging. We shall carry out pre engineering survey, pre & post construction survey, project management, construction services , design and detailed engineering, procurement of all material, manufacture, inspection, testing, supply, dismantling, fabrication, load out, tie down, hook up, packing, forwarding, transportation, site acceptance, pre commissioning, commissioning, installation, As-built, overall quality assurance & quality control, all warranties/guarantees related to this project | 03.12.2021 | 02.06.2024 | ||
HHI South Korea | BCP-A,BPA/BLQ-1 | Booster Compressor BCP-A Project-Hook Up and related modification BPA / BLQ-1 platform work relating to structural mechanical, piping, instrumentation, electrical & architectural, piping of approx. 6623 Inch Dia in C.S., DSS, SS. Replacement / Revamping of 37 Nos. Vessels of GDU system; cable laying of approx.138 kms, Installation of new DCS system etc. | Sep-98 | May-99 | ||
NPCC- Abu Dhabi | B&S-NH4 Well Platform Project-2 | Modification Works at Platforms HRG, HB, BLQ & BA including deployment of marine spread. The major works involved Structural, Piping, Electrical , Instrumentation, Mechanical works including Deck extensions, Receivers/Conectors, Installation of Knowout drupms and its Hook-up, Integration with existing DCS/PLC System with a provision of Marine spread. | May-06 | April-07 |